HDD project in Matachewan, ON
September 27th, 2011 by David

After a several trouble filled weeks of dealing with big cobbles and boulders under the Montreal River, the Marathon HDD team has succeeded in pulling the pipe through for the installation of a 14 inch Water Main. It was one of the toughest directional projects in the history of the directional division, and we are really proud of the team’s hard work and commitment. Bravo!
You can see the new DD10 in the background.